Client: Australian Lamb Colac

CTP Scope:

AC System Design / DC Configuration Design / Grid Connection Approval with Powercor / Supply of Protection Equipment

Timeframe:
  • Preliminary Phase: Jan 2017 – Mar 2017
  • Design Phase: May 2017 – Sept 2017
  • Construction Phase: July 2017 – Feb 2018
  • System Commissioning: Feb 2018
Project Goals:

To complete the entire AC design and deliver protection equipment for Sun Connect’s largest rooftop project as of 2018

Project Challenges:

Complex site with multiple arrays spread over 5 buildings. Arrays comprised of 13 different orientations coordinated into 3 MSB connections.
Each of the 3 connections required dedicated Powercor SCADA equipment integration.

Project Results:
  • Sun Connect’s largest solar PV rooftop at the time of commissioning
  • Efficient Powercor approval and commissioning stage