Client: Belectric

CTP Scope:
  • Preliminary Engineering Design,

  • Development Approval Co-ordination,

  • Grid Connection Engineering

Timeframe:
  • Preliminary Design Phase: 03/2016 – 06/2016
  • Development Application Phase: 07/2016 – 11/2016
  • Grid Application Phase: 11/2016 – 03/2017
  • Construction Phase: Expected Start 07/2017
Project Goal:

To establish a Development Approval and grid connection Offer-to-Connect for the Dareton/Coomealla Solar Park within a 12 month timeframe.

Project Challenges:

Co-ordinating multi-disciplined team (Engineering & Town Planning) to achieve development application and ensuring that grid connection timelines were met.
Existing site was old farm in close proximity location to adjacent houses. Extensive community consultation and Glare & Glint Studies were conducted to ensure neighboring properties were not affected.

Project Results:

Successful attainment of Development Approval and Grid Connection Offer within 12 months of being engaged.

Testimonials:

Nir Dekel, Vice President Sales & Operations
Belectric GmbH

“Working with CTP was very efficient and effortless. They kept us updated on key milestones and enabled the project to obtain Development Approval and Grid Connection seamlessly and with the highest quality making sure the costs are as cost-effective as possible.  We are very pleased with the outcome.”