Client:  Renew Power Group – Kevin Heydt/Thomas Parel

CTP Scope:
  • Contract Negotiation
  • Design Review
  • Technical Advisory Services
Timeframe:
  • Preliminary Phase: August – October 2018
  • Design Phase: Nov 2018 – Feb 2019
  • Construction Phase: Jan 2019 – April 2019
  • System Commissioning: May 2019
Project Goals:

Technical Advisory for the owner of 5MW solar farm in South Australia. Produced owner’s requirements and technical specification and acted as principal’s representative for review of design and construction.

Project Challenges:

Challenging project time frame. This required CTP to provide the client with direction to navigate their way through the full process of specifying project requirements, contract negotiation, design reviews and construction.

Project Results:

The project was successfully commissioned on time whilst maintaining installation quality.