7.2 MWp Timboon West Wind Farm, Timboon, VIC

Client: BayWa R.E. Renewable Energy CTP Scope: Preliminary Engineering Design Network Modeling Grid Application. Timeframe: Preliminary Phase: 01/2017 – 04/2017 Modelling Phase: 05/2017 – 08/2017 Construction Phase: TBC System Commissioning:…

80 kWp Burleigh Flowers (NX), Dandenongs, VIC

Client: Energy Australia CTP Scope: Grid Application with AusNet Services Grid protection equipment supply incl ramp control Injection testing Timeframe: Preliminary Phase: 02/2016 Design Phase: 03-04/2016 Construction Phase: 08/2016 System…