CTP Scope:
- HV Electrical Design
- Protection System Studies
- Earthing Design
Timeframe:
- Design Phase: 06/2017 – 08/2017
- Construction Phase: 08/17 – 12/17
- System Commissioning: 12/17-02/18
Project Goals:
To provide HV electrical engineering design services for the project including but not limited to:
- HV OHL Design
- HV Cable Studies
- Protection studies and system settings
- Earthing study and design
Project Challenges:
A fast paced design and build timeframe meant that we had to be flexible and responsive in meeting YD Projects timelines.
Project Results:
Australia’s first independently financed solar farm in and the largest solar farm in the world to use the novel Belectric PEG system.
One of the quickest solar farm builds in Australia with a build time of approximately 1MWp / week.