Client: Sun Connect

CTP Scope:
  • Grid application (Ausnet)

  • Construction drawings

  • Protection Switchboard Supply and

  • Commissioning.

Timeframe:
  • Preliminary Phase: 11/2016 – 03/2017
  • Design Phase: 04/2017 – 10/2017
  • Construction Phase: 11/17 – 04/18
  • System Commissioning:  04/18-05/18
Project Goals:

To install the second stage of Nature’s Organics’ 1.3MW rooftop solar system.

Project Challenges:
  • Fitting 700kW of panel capacity on a 80m x 80m roof space while installing around existing sky-lighting.

  • Coordinating with Nature’s Organics’ switchboard supplier to integrate the 1000A Solar Main Switch into the site’s new MSB.

Project Results:
  • The use of Trina TSM-DDO5A 300W high efficiency modules with a max power density of 183 W/m2 allowed the installation of 700kW of PV modules without installing over any skylights on the newly constructed building.

  • The 2 stages combined place the installation as the third largest rooftop system in Australia as of May 2018.