Client: Sun Connect
CTP Scope:
-
Grid application (Ausnet)
-
Construction drawings
-
Protection Switchboard Supply and
-
Commissioning.
Timeframe:
- Preliminary Phase: 11/2016 – 03/2017
- Design Phase: 04/2017 – 10/2017
- Construction Phase: 11/17 – 04/18
- System Commissioning: 04/18-05/18
Project Goals:
To install the second stage of Nature’s Organics’ 1.3MW rooftop solar system.
Project Challenges:
-
Fitting 700kW of panel capacity on a 80m x 80m roof space while installing around existing sky-lighting.
-
Coordinating with Nature’s Organics’ switchboard supplier to integrate the 1000A Solar Main Switch into the site’s new MSB.
Project Results:
-
The use of Trina TSM-DDO5A 300W high efficiency modules with a max power density of 183 W/m2 allowed the installation of 700kW of PV modules without installing over any skylights on the newly constructed building.
-
The 2 stages combined place the installation as the third largest rooftop system in Australia as of May 2018.